Our project Merrill Gardens at Rolling Hills Estates has made significant progress!

Merrill Gardens at Rolling Hills Estates is making great progress! The metal framing is almost complete with metal framing and the roof will be installed in May. The structural concrete is complete and framing is on the home stretch. They’ve started taking deliveries of the window and exterior building finish materials. More to come! Stay tuned.

More information on the project here.

IMG_0696.jpg
WIN_20190404_13_00_06_Pro.jpg
WIN_20190404_10_47_25_Pro.jpg

Our team is making great progress in Columbia, SC!

OUr team is making great progress at our project Merrill Gardens at Columbia, SC. Majority of our structural work is complete. The installation of windows and exterior brick are starting to take shape. Interior framing has started on the fourth floor and will allow for finishing from the top down.

Take a closer look at MG at Columbia, SC here.

Full Exterior

Full Exterior

Exterior Brick

Exterior Brick

Interior Brick

Interior Brick